1. Static Deodorising system

Milton Landfill site has installed a static deodorising system as part of its progressive odour management controls. This system is situated west of the site towards the Park & Ride facility opposite the operational area. The system uses a number of heads that spray a fine mist with an organic chemical which has the ability to trap odours as they fall to the ground rather than mask them with an additional perfume.

2. Daily Cover

As the site accepts waste the operational area moves which could lead to large areas of uncovered waste. FCC Environment has management procedures trained out to their staff to ensure that areas of the operational area that is not accepting waste if fully covered at all times using inert materials such as soils or clay. At the end of the daily operations cover is applied to the whole area.

The use of inert cover has the following positive effects:

1. Reduce the potential of odour from fresh waste deposits.

2. Reduce the potential of flies during the summer months.

3. Reduce the potential impact of scavenging pests.

4. Reduce the potential impact of wind blown litter.

3. Gas Control

The site Infinis andoperational staffmonitors the gas infrastructure on site on a regular basis toensure all is working at an optimal level. We also carry out regular inspections of all the wells to ensure they remain sealed and in a good state of repair.

During the operational fill stage we also install a network of horizontal pipework throughout the active areas which is
connected to the gas extraction system. Although these do not contain good quality landfill gas, they are used to apply a small amount of suction to the area helping with environmental and odour controls. These systems are sacrificial and will be replaced with appropriate gas wells once the areas are completed.

4. Capping

During the summer of 2014 we capped the top of Cell 19B.  Cell 19A is currently being capped and will be completed by March 2015.The site is progressively capped as each phase is completed. We are also currently building a new cell 21A which will be completed in march 2015.

Keeping local residents informed

FCC Environment along with the Milton Parish Council is planning to commence an inaugural Community Liaison Group for Milton Landfill. It will help to keep local residents up to date with what FCC are doing at the site and allows local residents to be regularly briefed on the site operations and answer any issues raised.

A Milton Landfill Webpage and an “out of hours” free phone system is to be launched in order to allow the Milton residents to view all current and proposed plans for the site. The “out of hours” free phone will allow residents to leave an out of hour’s message if they have any queries or complaints. These will be responded to at the start of the next working day.

December 2016

  • Waste continues to be disposed of in cell 22

  • Operations, Environment & INFINIS team continue to monitor and manage gas & Leachate collection systems

  • Operations continue to monitor for any emissions/odours

  • Additional gas horizontal installed in to cell 22

  • Continuation of soil placement on cell 14

  • Stockpiling of soils for cell 19A restoration

  • Numerous leachate pump exchanges

  • Installation of 6 new leachate pump

  • Continue with 2 road sweeper daily

  • Continue with weekly site infrastructure checks 

July - November 2016

  • Construction of cell 22

  • Permanent capping of 19A

  • Temporary capping of 21A

  • Retro drilling of 6 Leachate wells

  • Continue odour asessments in key areas

  • Further improvements to the site installation logs

  • Further re-training of site plant operators on the construction of flanks- soils to be placed first waste to be fill to it. The flank of cell 22 filled to a 1:3 landform to ensure there is suitable stability

  • Working manageable tipping areas incorporating sufficient soil placement in non- operational areas

  • Reintroduced concrete rings on to the leachate wells when there is the requirement to raise them including suitable soil placement around the rings to minimise voids and

  • Reinstated the wheel bath following extensive repairs

  • Introduced a weekly site field check sheet to capture issues at the earliest opportunity

  • Introduced more rigorous inspection of the leachate tanks (3 times per day)

June 2016

  • Waste disposal operations continuing in cell 19A & 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Soil placement still ongoing in cell 14

  • Mischantus grass has been bailed and sent to burner

  • Exsisting gas infrastructure on cell 21/21A connected and operational  

  • Local liaison meeting with Milton parish on site went well good feedback

  • Capping and new cell build to start in June 13/06/2016, confirm date when local parish council come to site to have a look at new cell build.

May 2016

  • Waste disposal operations continuing in cell 19A & 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Soil placement still ongoing in cell 14

  • Mischantus grass has been bailed and sent to burner

  • Exsisting gas infrastructure on cell 21/21A connected and operational

  • Local liaison meeting with Milton parish on site went well good feedback

  • Capping and new cell build in June date TBC

April 2016

  • Waste disposal operations continuing in cell 19A & 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Soil placement still ongoing in cell 14

  • Mischantus grass has to be cut and ready to be bailed

  • Exsisting gas infrastructure on cell 21/21A connected and operational  

  • Local liaison meeting with Milton parish on site, 27th April, provided positive feedback click here for minutes

March 2016

  • Waste disposal operations continuing in cell 19A & 21 to the north east of the site ,also stripping soil off on cell 19A

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Relocate Leachate pipe work in cell 14 due soil placement

  • Existing Gas infrastructure on cell 21/21A connected and operational

  • Gas main line isolation disconnection & relocation /installing into the waste ,of cell 19A ( all connected)

  • 10 new Gas well are planned for 22nd March in cell 21/21A, the Drillers will start work on this date for about two weeks work  

  • Looking to hold the next Local liaison meeting committee sometime in April (Onsite)

February 2016

  • Waste disposal operations continuing in cell 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Relocate Leachate pipe work in cell 14 due soil placement

  • Existing Gas infrastructure on cell 21/21A connected and operational

  • Gas main line isolation disconnection & relocation /installing into the waste ,of cell 19A ( 4/3/2016)

  • Gas well drilling is planned for April/ may (will have confirm date by the end of March) 

January 2016

  • Waste disposal operations continuing in cell 21 to the north east of the site

  • Operations ,Environment and Infinis Teams continuing to monitor for odour in operational areas, site          perimeter and residential area

  • Relocate Leachate pipe work in cell 14 due soil placement

  • Existing Gas infrastructure on cell 19/21/21A connected and operational

  • Clay exporting took place the first week of the month for one week

  • Gas well drilling  is planned for April/ may

October 2015

  • Waste disposal operations continuing in cell 21A (new cell) to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Infinis we continue to put it sacrificial  pipe work  (scavenger & horizontal installation) as we move in to the new cell 21A with waste, Scavenger well installed next to the operational area, connection  to gas extraction system

  • The third local liaison meeting committee will be held on the 20th  October , this will included a site visit  and incorporate a site visit to Infinis gas compound - this meeting  went well  on site  and everyone was happy what has done – please see attached the Liaison meeting minutes

September 2015

  • Waste disposal operations continuing in cell 21A (new cell) to the north east of the site,

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Infinis we continue to put it sacrificial  pipe work  (scavenger & horizontal installation) as we move in to the new cell 21A with waste, Scavenger well installed next to the operational area, connection of L26B to gas extraction system

  • The third Local liaison meeting committee will be held on the 20th  October , this will included a site visit  and incorporate a site visit to Infinis gas compound

  • Installing 6 new leachate pumps in the new well that we have had re-drilled

August 2015

  • Waste disposal operations continuing in cell 21A (new cell) to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Drilling 6 new leachate wells will start 14/8/2015 and work will finish on the 21/8/2015 (6 working days) works completed on time

  • Infinis we continue to put it sacrificial pipe work (scavenger & horizontal installation) as we move in to the new cell 21A with waste, Scavenger well installed next to L26B,L32,L32A in operational area, connection of L26B to gas extraction system

July 2015

  • Waste disposal operations continuing in cell 21 to the north east of the site, this area will be finished by the Aug The waste disposal operations will then moving in to the new cell 21A

  • Operations ,Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Drilling 6 new leachate wells will start 14/8/2015 and work will finish on the 21/8/2015 (6 working days)

  • The third Local liaison meeting committee will be held in September, this will included a site visit and incorporate a site visit to Infinis gas compound- this meeting went well on site

  • Infinis we continue to put it sacrificial pipe work (scavenger & horizontal installation) as we move in to the new cell 21A

June 2015

  • Waste disposal operations continuing in cell 21 to the north east of the site

  • Operations ,Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Retro drilling for the gas wells on cell 19A went well finish on the 5/6/2015 (4 working days)

  • Relocate Leachate pipe work in cell 19B,19A and also some pump exchanges

  • L27B and L28B are being re-drilled July/August 2015

  • Infinis have installed 3 x scavenger wells installation in 19B

  • Z1504- 60m horizontal installation into current tipping area (21)

May 2015

  • Waste disposal operations continuing in cell 21 to the north east of the site.

  • Operations ,Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area.

  • Local liaison meeting committee will be held on 20th may at Milton village, this will included a site visit and incorporate a site visit to Infinis gas compound- this meeting went well on site.

  • See attached for the minuets from the last two meeting --- 9th march and 20th May.

  • Retro drilling for the gas wells on cell 19A will start 2/6/2015 and work will finish on the 5/6/2015 (4 working days).

  • Relocate Leachate pipe work in cell 19B,19A

April 2015

  • Waste disposal operations continuing in cell 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Engineering contractor have re-mobilised and completed further Temporary (plastic) capping on 19A/19B corner and flaks (northern /eastern)

  • The second Local liaison meeting committee will be held on 20th may at Milton village, this will included a site visit  and incorporate a site visit to Infinis gas compound

  • Drilling of additional gas well on cell 19A will may be in early June

  • Existing Gas infrastructure on cell 19a reconnected and operational when the Engineering works was taken place  

March 2015

  • Waste disposal operations continuing in cell 21 to the north east of the site

  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential area

  • Engineering contractor have finished the capping on 19A/19B flaks on the eastern side, but are coming back to do temp capping works on 19B/19A corner

  • The first Local liaison meeting committee held on 9th March at Milton village

  • Relocate Leachate pipe work in cell 14 due soil placement

  • Existing Gas infrastructure on cell 19a/19b connected and operational   

 