November 2014

  • Waste disposal operations continuing in cell 4b and 6c to the north of the site.
  • Additional gas infrastructure installed on cell 4b now connected into main gas collection system, further gas infrastructure to be installed when tipping operations cease.
  • Odour control system fully operational.
  • Placement of restoration soils on going on area B1/C2 North to the north west of the site.
  • Engineering works commenced on site including capping of cell 4b and lining of the cell 7 internal flank
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling complete.

 

October 2014

  • Waste disposal operations continuing in cell 4b and 6c to the north of the site.
  • Additional gas infrastructure installed on cell 4b now connected into main gas collection system, further gas infrastructure to be installed when tipping operations cease.
  • Odour control system fully operational.
  • Placement of restoration soils on going on area B1/C2 North to the north west of the site.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling complete.

September 2014

  • Waste disposal operations continuing in cell 4b to the north of the site. Tipping commenced in newly approved cell 6c.
  • Additional gas infrastructure installed on cell 4b with connection works on-going, further gas infrastructure to be installed when tipping operations cease.
  • Odour control system fully operational.
  • Capping of area B1/C2 complete and restoration soils being placed.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling commenced with the Newt Fencing constructed and Newt trapping underway.
August 2014
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Gas infrastructure for 4b installed and connected into main gas system.
  • Plans for further gas infrastructure on cell 4b being progressed.
  • Odour control system fully operational.
  • Engineering works to construct next waste cell 6c complete, CQA report submitted to Environment Agency approval likely mid-September.
  • Capping of area B1/C2 complete and restoration soils being placed.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling commenced with the Newt Fencing constructed and Newt trapping underway.

July 2014
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Gas infrastructure for 4b installed and connected into main gas system.
  • Odour control system fully operational.
  • Engineering works to construct next waste cell 6c complete, CQA report submitted to Environment Agency with site awaiting approval to commence tipping operations
  • Capping of area B1/C2 complete and restoration soils being placed.
  • Remediation works to cell 7 temporary capping complete with continued monitoring to check the integrity of the cap on-going.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling area due to commence August 4th.

June 2014

  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Gas infrastructure for 4b planned for install summer 2014 on schedule.
  • Odour control system fully operational. Options to extend the system for next cell being reviewed.
  • Engineering works to construct next waste cell 6c progressing to schedule with approximately 90% of works complete.
  • Capping of area B1/C2 now complete ready for restoration soils.
  • Remediation works to cell 7 temporary capping commenced.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter
    and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling area due to commence August 4th.

May 2014
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Gas infrastructure for 4b planned for install summer 2014 on schedule.
  • Odour control system fully operational. Options to extend the system for next cell being reviewed.
  • Engineering works to construct next waste cell 6c progressing to schedule with approximately 85% of works complete.
  • Capping of area B1/C2 now complete ready for restoration soils.
  • Remediation works to cell 7 temporary capping planned and scheduled for June/July; these works will help maintain environmental control.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes, Central Beds and trade waste customers.
  • Ecology works relating to the wood recycling area due to commence mid/end of July.
 
 
April 2014
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Gas infrastructure for 4b planned for install summer 2014.
  • Odour control system fully operational.
  • Engineering works to construct next waste cell 6c underway and progressing to schedule.
  • Capping of area B1/C2 underway and progressing to schedule
  • 10 x new gas wells drilled on cell 7 completed and connected in to main gas system.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes and Central Beds.
 

March 2014
  • Waste disposal operation continuing in cell 4b to the north of the site.
  • Further gas infrastructure installed in cells 5 and 6 to increase the gas control and provide enough infrastructure to manage future cell 4b and 6c. This infrastructure is now fully operational.
  • Odour control system fully operational.
  • Engineering works to construct cell 6c commenced and progressing well, weather permitting this will be a 16 week project.
  • Drilling of additional wells on cell 7 due to commence 31st March, all existing infrastructure on cell 7 connected and operational.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • Use of the old entrance at Newton Longville has now ceased as the main haul road through site has been repaired and is now serviceable.
 


February 2014
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Further gas infrastructure currently being installed in cells 5 and 6 to increase the gas control in this area and provide enough infrastructure to manage future cell 4b and 6c.
  • The new odour control system on the north side of site has now been installed and is fully operational.
  • Engineering of next waste cell 6c due week commencing 10th Mar 2014, this will be a 16 week project [weather permitting].
  • Further gas infrastructure planned on cell 7, will be installed subject to weather allowing access. All existing infrastructure connected and operational.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • Use of the old entrance at Newton Longville has now ceased as the main haul road through site has been repaired and is now serviceable.


 
October 2013
  • Waste disposal operations continuing in cell 4b to the north of the site.
  • Engineering works currently progressing/complete on site include; cell 7 temporary capping [now complete], cell 7 bund and surface water remedial works [now complete], internal haul road repairs on-going, permanent capping of areas B1 and C2 continuing but weather slowing progress.
  • Further gas infrastructure planned on cell 7, this will be installed subject to weather allowing access. All existing infrastructure re-connected and operational.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes and Central Beds.
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for repairs to site haul road are developed. Works to repair road are scheduled to commence in early October.
  • Works for the installation of the odour control system have commenced with completion scheduled for mid December.
 


September 2013
  • Waste disposal operations ceased in Cell 7 with this area now being temporarily capped.
  • Waste disposal operations continuing in Cell 4b to the north of the site.
  • Engineering works currently progressing on site include; Cell 7 temporary cap, Cell 7 bund and surface water works, internal haul road repairs and permanent capping of areas B1 and C2. During the temporary capping of Cell 7 the gas infrastructure will be disconnected and re-connected keeping as much control on the system as possible.
  • Upon completion of the capping works further installation of gas infrastructure will be considered to improve environmental control.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF operational. The facility is accepting waste from Milton Keynes and Central Beds.
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for repairs to site haul road are developed. Works to repair road are scheduled to commence in early October.
 

  
August 2013
  • Waste disposal operations continuing in cell 7 and 4b.
  • All available gas wells on cell 7 connected and under suction to minimise odour.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • Capping of cell 7 scheduled for September.
  • MRF commissioning now complete and operational. The facility is accepting waste from Milton Keynes and Central Beds.
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for repairs to site haul road are developed. Works to repair road are scheduled to commence in September.

July 2013
  • Waste disposal operations continuing in both Cell 7 and Cell 4b.
  • All available gas wells on cell 7 connected and under suction to minimise odour.
  • Further gas infrastructure installed on northern flank of cell 7. There is now a total of 33 extraction well plus 10 shallow pin wells on cell 7.
  • Operations, Environment and Infinis Teams continuing to monitor for odour in operational areas, site perimeter and residential areas.
  • MRF in final stages of commissioning with plant processing waste from Milton Keynes and Central Beds.
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for repairs to site haul road are developed. Works to repair road are scheduled to commence in September.
 

June 2013
 
  • Waste disposal operations in cell 7 continuing but at a reduced rate due to space for vehicles and plant, waste inputs into cell 4b increasing.
  • All available gas wells on cell 7 connected to minimise odour.
  • Operations and Environment Teams continuing to monitor for odour on perimeter boundaries, operational areas and residential areas.
  • MRF commissioning process on-going with the plant processing waste from Central Beds and Milton Keynes.
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for repairs to site haul road are developed
  • Further gas infrastructure on cell 7 planned for early July.


May 2013
 
  • Waste disposal operations in cell 7 continuing with waste also being accepted into the recently engineered cell 4b.
  • Operations ensuring all available gas wells on cell 7 are connected to minimise odour.
  • There is continued odour monitoring on the perimeter boundaries, operational areas and residential areas.
  • The MRF commissioning process is continuing with the plant processing waste from Central Bedfordshire and Milton Keynes
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for the new perimeter road is developed.
  • Successful visit from the HSE on the 21st May

April 2013
  • Waste disposal operations continuing in cell7
  • Further gas well on cell 7 internal slopes and bench complete bringing total number of gas extraction wells on cell 7 to 33.
  • There is continued odour monitoring on the perimeter boundaries, operational areas and residential areas.
  • The MRF commissioning process is underway with the plant processing waste from Central Bedfordshire
  • There is continued use of the old entrance gates for access to rear of site whilst remedial works and engineering design for the new perimeter road is developed.

March 2013
  • Waste disposal operations have continued in cell 7.
  • Monitoring of the capping works and gas well drilling projects carried out in cell 7 has identified areas for further works.
  • Engineering contractors have re-mobilised’ and completed further temporary capping works on areas of the cell 7 internal slopes.  These works also included the placement of a clay access bench that will enable further gas well drilling to be completed on areas that were previously difficult to access.
  • Further gas well drilling has taken place in the operational cell 7 and all gas well has been connected.  More drilling will be completed in April along the newly constructed clay bench.
  • The capping and gas well drilling works have targeted areas of potential odour release within the operational area.  Ongoing monitoring will take place to determine the effectiveness of these works.
  • Additional horizontal gas pipework has been installed and connected within the operational cell.
  • Odour monitoring of the perimeter boundaries, operational areas and residential areas has continued during March.
  • The MRF installation is nearly completed and commissioning is due to take place in April where it will be expected that household waste will then be diverted from landfill to the MRF operation
  • Continued use of the old entrance gate for access whilst remedial an engineering design and new perimeter road proposals are developed


February 2013
  • Continued waste disposal in the operational Cell 7
  • Temporary capping works on the internal slope of cell 7 have been completed.
  • The recently drilled gas wells have all been connected to the main system forming part of the ongoing gas control system for the operational area.
  • Ongoing gas and odour monitoring taking place around the operational area to identify any areas of temporary capping or infrastructure that require further works to minimise the potential for a release of odours.
  • Continued perimeter monitoring taking place as well as off site monitoring around residential areas.
  • Local liaison meeting held on 26th February at the Bletchley office.
  • Construction of the Materials Recycling Facility (MRF) is ongoing with the mechanical equipment install taking place.  This involves the fitting of shredders, bailers, conveyors and other processing equipment required for the facility.
  • Construction of the next operational cell (Cell 4B) completed.  This cell is located to the north of the site and upon Environment Agency approval waste disposal will commence in this cell.  This is expected in April or May 2013.


January 2013
  • Waste disposal continues in Cell 7 located to the south east of the site.
  • High level access road to cell 7 now in use along the eastern boundary.
  • Survey work ongoing and engineering plans under review in association with the material slip within the clay dig.  This slip has impacted the internal tarmac access road resulting in diversion of non waste delivery traffic to use the old entrance gate off Bletchley Road and Newton Road.  Contractors light vehicles, delivery vehicles and tankers associated with the leachate treatment plant operation all require access via this route.
  • The temporary capping works on the internal waste slope of Cell 7 have re-commenced following improvements to weather that had impacted access and safe operations for these works during November and December.  These planned works form part of the ongoing measures to control potential odours associated with operations on the site.
  • Gas well drilling commenced and completed within Cell 7 operational area.  Gas wells will be connected to the main system in February.  These planned works form part of the ongoing measures to control potential odours associated with operations on the site.
  • Ongoing odour and gas monitoring taking place around the operational area of cell 7 and along site boundaries and residential areas.